Active and future projects in Rodrigues.
Construction of 2 x 1000 m3 circular concrete reservoirs at Pointe Coton
• Awarded to Laxmanbhai & Co (Mauritius) Ltd
• Date of award : 22 January 2024
• Amount : 44,654,314.45 + VAT
• Expected completion Date :25 May 2025
• Progress of work (%) :30%
Pictures below:

Construction of Building of 1045 m2 for desalination plant at Pointe Coton
• Awarded to Marday Calleemallay Construction Ltd
• Date of award : 04 January 2024
• Amount : 44,500,000.00 + VAT
• Expected completion Date :30 January 2025
• Progress of work (%) :35%
Pictures below:
Drilling, Testing and Construction of 12 Boreholes and Associated Works at Various Locations in Rodrigues
• Awarded to Water Research Co Ltd
• Date of award : 04 January 2024
• Amount : 14,233,700.00 + VAT
Drilling started on 19 July 2024.
List of completed and ongoing sites:
| Site | Number of boreholes | Status |
|---|---|---|
| Pointe Coton | 4 intake boreholes 1 rejection borehole |
Drilling completed |
| Araucaria | 1 intake borehole | Drilling completed |
| Papayes | 1 intake borehole | Drilling completed |
| Montagne Cabris | 1 intake borehole | Drilling completed |
| Caverne Bouteille | 2 intake boreholes | Drilling completed |
| Anse Aux Anglais | 1 intake borehole | Drilling completed |
Pictures below:


Design, Supply, Installation, Commissioning and 1 year Operation of a 3000 m3/day Sea Water Reverse Osmosis Plant and Associated Works at Pointe Coton, Rodrigues.
• Expected Awarding Date :October 2024
• Expected completion Date :October 2025
Supply and Laying of Main Transfer Pipeline from Pointe Coton Desalination Plant to Petit Brulé Reservoir
• Expected Awarding Date :October 2024
• Expected completion Date :November 2025